May 31, 2023 Update
The following is the look ahead schedule for the 4825R North Wrap Up Contract:
- Concrete pours taking place for driveways at Sunnyside and Agatite
- Catch basin installations at Sunnyside and Agatite
- Look ahead includes:
- Drain tile installations at Berteau and Agatite
- Earthwork construction plan is being approved
===========================================================================================
May 24, 2023 Update
Look ahead schedule for the 4825R North Wrap Up Contract:
- Project submittals and approvals are ongoing
- Work has begun off local roads in Schiller Park including the following:
- Fence and guardrail removals
- Cleaning and site prep
- Driveway removals
- June 2023:
- Work anticipated to begin at Lawrence Avenue bridge, approximately 3 days of single lane closures are needed for each direction, subject to change.
===========================================================================================
Resident Notification Letter
====================================================================================
May 10, 2023 Update
The following is the look ahead schedule for the Northern Area I-294 Wrap Up Contract:
- Project submittals and approvals are ongoing
- Second week of May:
- The following is the look ahead schedule for the Northern Area I-294 Wrap Up Contract:
- Existing conditions surveying
- Layout and local roads MOT set up
- June 2023:
- Work anticipated to begin at Lawrence Avenue bridge, approximately 3 days of single lane closures are needed for each direction, subject to change.
Notices will be delivered later this week or early next week to impacted Village residents.
If you have any questions, please let me the Village know at (847) 678-2550.
========================================================================================
Tollway Project Wrap Up - Spring 2023
A pre-construction meeting for the work adjacent to Schiller Park was held Wednesday. The contractor indicated they plan on starting the work in May of 2023. The Village will get a schedule from the contractor as we approach the start of the work. In the meantime, it appears road closures will be needed at Lawrence Avenue to do the bridge work. The Tollway will keep the Village updated on the MOT and the Tollway may issue a press release for it. The Tollway will learn more when the contractor tells us know how many days they will need to be out there with the closures.
Residents along the local roads, where the work is to take place, will be notified. This includes Sunnyside, Berteau, Denley and Agatite. Further updates will be provided as the work proceeds.